2018

·

Grid

Kestrel substation retrofits

New protection relays at 14 live substations on a regional network.

14 substations,

no unplanned outage

A substation transformer among steel gantries under broken cloud

Size

14 substations, 110 kV

Location

Northern Germany

My role

Protection design and site lead

Team

4 engineers, 2 site crews

Duration

31 months, 2016 to 2019

01

The situation

Kestrel looked after a regional 110 kV network in northern Germany. Fourteen of its substations still ran on mechanical protection relays from the 1970s and 1980s. These are the devices that detect a fault and tell a breaker to open. Spare parts had run out, and only two technicians still knew how to calibrate them.

The substations fed towns, a port and two hospitals, so none could be switched off for more than a few hours. The relays had to be replaced while the stations stayed live. A wrong setting in a new relay does not show on the day. It shows months later, as a blackout nobody expected.

02

What I did

I designed the new protection scheme for each substation and calculated the settings for 212 digital relays. I checked each setting against a model of the network in PowerFactory. Then a second engineer checked it without seeing my numbers. Where our answers differed, we stopped and worked out why before anything was ordered.

On site, we replaced one section at a time while the others carried the load. I wrote a switching plan for every outage and agreed it with the control room a week ahead. I stayed at each substation until its last relay had been tested by feeding in a simulated fault and watching the breaker open.

03

What changed

All 14 substations were upgraded between 2016 and 2019 with no unplanned outage. Every planned outage was handed back on time or early. In the first winter after the work, the new relays cleared three real faults on overhead lines. Each one was cleared in under a tenth of a second, and only the faulty line was switched off.

The double check on settings became a rule in Kestrel’s design office. It added about a day per substation and found nine errors before they reached site. Four of them were mine. I have used the same rule on every battery project since. It is the cheapest insurance I know.

14

Substations upgraded while live

2016 to 2019, 110 kV network

212

Protection relays replaced

Each setting checked by two engineers

0

Unplanned outages during the work

Control room outage records

Rows of high-voltage insulators at a substation
A transformer bay under a blue sky

“She would not leave a station until she had seen every breaker open with her own eyes. Our control room trusted her switching plans completely.”

Annika Dreyer

Head of Network Operations, Kestrel Grid Services