Norrvind Offshore

·

2016

·

Wind

Havbrise array cables

Test programme for a 54-turbine offshore wind farm.

48 km

tested, no rework.

Offshore wind turbines in a line on a calm blue sea

Size

54 turbines, 48 km of 66 kV cable

Location

North Sea, 30 km off western Norway

My role

Graduate engineer, cable testing

Team

5 in the cable team, 2 vessel crews

Duration

21 months, 2014 to 2016

01

The situation

Havbrise is a 54-turbine wind farm off the west coast of Norway. The turbines are linked to the offshore substation by 54 lengths of 66 kV array cable, 48 km in total, buried in the seabed. I joined the cable team straight from university in September 2014, a year before the first cable was laid.

Array cables are a common source of insurance claims in offshore wind. A fault found after burial means bringing a vessel back, at a cost of around 150,000 USD a day. The project had no single test programme. The factory, the installer and the owner each had their own plan, with gaps in between.

02

What I did

My manager gave me the test programme to run. I mapped every test each cable would see, from the factory floor to the seabed. I found two points where nobody was responsible for checking the cable at all. One was straight after loading onto the vessel. I added a test of the outer sheath at both points.

I witnessed the factory tests for all 54 lengths and spent eleven weeks offshore during installation. After each cable was pulled into a turbine and connected, we tested it before the vessel moved on. I kept one record sheet per cable, with the same fields in the same order, so a problem would show up as a number out of line.

03

What changed

All 48 km passed the final high-voltage test at the first attempt. No cable had to be reconnected, repaired or replaced, which the installer told us was a first for them. The sheath test after loading caught one damaged cable drum while it was still in port, where swapping it took a single day.

The farm exported its first power in the summer of 2016, on schedule. My record sheets went into the owner’s handover pack and were used again on Norrvind’s next project. This job taught me that testing is mostly planning. The offshore part only works if the paperwork was right six months earlier.

48 km

Array cable tested

54 lengths of 66 kV cable

0

Cables reworked after installation

Final high-voltage test results

11 weeks

Spent offshore during installation

Vessel rotations, 2015 to 2016

Offshore wind turbines on a green sea under cloud
Offshore wind turbines seen from the air